Situation:

BOND provided construction management services for the 7,600 SF fit-out of the L3 Chemistry Laboratory. The project included open lab spaces, write-up stations, tissue culture rooms, chemical storage libraries and an environmental room.

Challenges:

  • Work completed around occupied chemistry labs
  • Fire at epoxy manufacturing plant caused supply issue with custom colored epoxy tops

Solutions:

  • Tightly-planned coordination with team to plan shutdowns and switchovers
  • Provide standard color only at fume hoods to allow easier coordination and ordering of work and enable project to receive custom color epoxy tops

Results:

  • No disruption to neighboring chemistry labs
  • All lab benches installed as designed